Idaho Falls, ID – On Wednesday, March 13, 2019, 3H Construction will begin construction on the 9th Street Bridge over the Moody Canal. Barring unforeseen conditions, the anticipated completion time is 45 days.
The roadway from St. Clair Road east to Austin Avenue will be intermittently closed to vehicle traffic for the duration of the project. Pedestrian traffic will be uninterrupted.
This project consists of removing and replacing the existing bridge structure. New pipes, drainage, curb and gutter will also be installed.
Please observe all traffic control signs and detours. Your patience and cooperation is greatly appreciated during this process.
If you have any questions, contact Reed Hill at (208) 589-7713 or Idaho Falls Public Works at (208) 612-8250.