Over the next 60 days, HK Contractors will be making improvements on three separate roadways in Idaho Falls. Motorists are asked to not park on these roadways during construction or risk having their vehicles towed.
Beginning on Tuesday, July 6 on Stonebrook Lane, from Sunnyside Road to 100 feet past Cobblestone Lane, construction crews will be removing and replacing ADA ramps, paving streets, and adjusting manholes and water valves.
Beginning Monday, July 12, they will be working on Troy Avenue, from Broadway to Darah Street. The work entails removing asphalt, installing new drain inlets, placing base gravel to establish new elevations, paving streets, and adjusting manholes and water valves.
Improvements on the alley behind the Museum of Idaho, from Elm Street to Ash Street, begin on Monday, July 29. The contractor will be paving the alley and adjusting manholes and water valves.
Please do not park on these streets during construction, reduce speeds, obey posted traffic control signage, and watch for construction crews throughout the work zone.
For questions or concerns about this project, contact HK Contractors at (208) 523-6600.
Additional information on City of Idaho Falls construction projects can be found on the homepage of the city’s website or by clicking HERE.
Media Contact: Kerry Hammon, Public Information Officer, (208) 612-8122 or khammon@idahofallsidaho.gov.